Ordon's Orvis Building

Project Summary

HVAC Heating Water System Renovation

Escambia County had (3) existing boilers serving their downtown government complex. Only 1 of these boilers was actually functional. There was a clear lack of redundancy and efficiency with the current boiler system. The equipment was beyond repair, thus facilitating the need to replace the boilers in an expedited fashion to provide adequate heat for workers during the winter months.

  • Escambia County
  • 213 Palafox Place, Pensacola, FL 32502
    • HVAC heating water system renovation

    • Replaced (3) boilers and primary/secondary pumps with VFDs

    • New boiler controls and safety interlocks

    • All new combustion air and flue vent stacks

    • Complete mechanical room piping replacement, including air separator & expansion tank

    • Third-party test & balance

    • Full commissioning for optimal energy performance

    • Aerco Benchmark Boilers (Aerco Benchmark 3000 Boilers)
    • TACO Pumps (FI2009D 5HP Pumps and FI3011D 20HP Pumps)
    • Trane Tracer Building Automation System
  • 60 Days - The project was scheduled for 60 days. While the calendar spanned 74 days, 26 days were paused for equipment delays, so actual work was completed in 48 days.
  • Completed on a tight schedule during winter, coordinating with the owner to ensure uninterrupted heat for end users.

The Challenge

The main challenge of this project was created by the time of year these boilers were being replaced. We had to get heat back on the building as fast as possible or the end-user would have had a substansail impact to their day to day functions. Another challenge was the created by the mechanical room location and the location of the building. 

This building is located in a busy part of town and the mechanical room is nestled between their drive-through lane and parking garage. The majority of this work was completed during the buildings hours of operation so tight coordination was required.

the solution

This project required precise planning and execution of our work. Scheduling around anticipated lead times for the new equipment allowed us to utilize our prefab capabilities to help minimize time onsite. We utilized skilled pipefitters and welders to do this project, ensuring no mistakes were made during installation. 

The Air Design Systems team working together with the owner alloed us to deliver a functional finished product on time.

The Benefits

We followed the PAS rule when selecting the equipment on this project (Price Availability Specification). This essentially translates into: the equipment we selected is of a high quality that we can stand behind, while also having the availability/lead time to meet the shortest turnaround time for the owner, and fit within the budget

  • The equipment we selected is of a high quality that we can stand behind
  • The new system is more efficient and reliable than the previous system
  • The owner will experience energy savings while having a system they can rely on for years to come
Air Design Systems Air Design Systems

the team's take

 "The owner needed a fast renovation done to their existing HVAC Heating Water System. We provided exactly that." - Colby Wells, Project Manager

commercial strength. personal service.

designing comfort since 1977
  • By submitting, you agree to receive text messages from Air Design Systems at the number provided, including those related to your inquiry, follow-ups, and review requests, via automated technology. Consent is not a condition of purchase. Msg & data rates may apply. Msg frequency may vary. Reply STOP to cancel or HELP for assistance. Acceptable Use Policy